Road & Bridge Task 9 Work

Task 9, 2009 Road Work on Mustang Mesa is Complete
- Task 9.1 - Mustang Mesa south completed
A 0.25 mile section of Mustang Mesa south of Palomino was completed. This included complete replacement of the existing road bed with 8 inches of new base, ribbon curbs on both sides and two inches of asphalt.
- Task 9.2 - Mustang Mesa north completed
A 0.15 mile section of Mustang Mesa in the north part of the ranch was completed. This included complete replacement of the existing road bed with 8 inches of new base, ribbon curbs on both sides and two inches of asphalt. In addition, the drainage bridge was capped with concrete.