Task 9, Road Work on Mustang Mesa is Complete
- Task 9.1 - Mustang Mesa south completed
A 0.25 mile section of Mustang Mesa south of Palomino was completed. This included complete replacement of the existing road bed with 8 inches of new base, ribbon curbs on both sides and two inches of asphalt.
- Task 9.2 - Mustang Mesa north completed
A 0.15 mile section of Mustang Mesa in the north part of the ranch was completed. This included complete replacement of the existing road bed with 8 inches of new base, ribbon curbs on both sides and two inches of asphalt. In addition, the drainage bridge was capped with concrete.
Task 8, Road Work has Been Completed
- The Phase I chip-seal work in the south ranch was completed during the week of 9/29/2008.
Task 7, Road Work has Been Completed
- During the fall of 2007 and winter of 2007-08, the road repair project Task 7 was
completed. Scope was complete rebuild of Paint Pony, rebuild of
one driveway and installation of a “low water crossing” to
allow better drainage, five patch repairs on Mustang Mesa, and
a 50’ rebuild on Buckskin. There was one approved change
order for additional patchwork on Mustang Mesa and an extension
of the repair on Buckskin.
- Rayburn did an outstanding job as inspector for the road project.
His many years (we won’t say how many) of highway inspection
for TxDOT presented us with the opportunity to have a real professional
on the job each day to insure the owners got a top quality job.
- This work is now completed.
- You can view the work that has been done on these three roads
at R&B-Report Task 7 Work